By: Zaffirini S.B. No. 34

A BILL TO BE ENTITLED

AN ACT

relating to county authority to regulate the development of certain large electricity users.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1 Chapter 231, Local Government Code, is amended by adding Subchapter N to read as follows: Added text: SUBCHAPTER N. COUNTY REGULATION OF LARGE-LOAD ELECTRICITY USERS (End of added text)
Added text: Sec. 231.301. DEFINITIONS. In this subchapter: (End of added text)
Added text: (1) "Large computational load facility" means a tract or one or more contiguous or noncontiguous tracts of land under common ownership or control that are developed or proposed for development for use by a large computational load. (End of added text)
Added text: (2) "County large computational load zoning district" means a zoning district established under this subchapter. (End of added text)
Added text: (3) "Large computational load" means a business that: (End of added text)
Added text: (A) is primarily engaged in: (End of added text)
Added text: (i) creating, executing, and delivering software applications and services; (End of added text)
Added text: (ii) artificial intelligence training, deployment, and delivery; (End of added text)
Added text: (iii) adding virtual currency transactions to a distributed ledger; or (End of added text)
Added text: (iv) other computational activities at a data center; and (End of added text)
Added text: (B) is a large load under Section 37.0561, Utilities Code; or (End of added text)
Added text: (C) a substation, transmission or distribution facilities, or other electric infrastructure designed to serve the facility or project; and (End of added text)
Added text: (D) in determining whether a facility or project meets the requirements of Paragraph (B), the county may aggregate related facilities, phases, contiguous or noncontiguous tracts, meters, or projects that are under common ownership or control or are developed, financed, constructed, or operated as part of a common plan. (End of added text)
Added text: (4) "Project" includes the construction of a new large computational load or a material expansion, redevelopment, or change in the use of an existing facility. A material expansion is an increase in electricity demand of at least 10 megawatts. (End of added text)
Added text: Sec. 231.302. APPLICABILITY. This subchapter applies only to the unincorporated area of a county. (End of added text)
Added text: Sec. 231.303. AUTHORITY TO ESTABLISH LARGE COMPUTATIONAL LOAD ZONING DISTRICTS. (a) To protect the public health, safety, and welfare, promote the orderly development of the county, and ensure that county residents benefit from large computational load development, the commissioners court may establish one or more county large computational load zoning districts and regulate the location and development of large computational load and large computational load within a district consistent with this subchapter. (End of added text)
Added text: (b) A district may include all or part of the unincorporated area of the county. The boundaries of the district must be described by metes and bounds or shown on a map adopted as part of the order establishing the district. (End of added text)
Added text: (c) A zoning district or district boundary is not effective until adopted by the commissioners court after a public hearing. Before adopting a district or district boundary, the commissioners court shall provide public notice and hold a public hearing in accordance with procedures adopted by the court. (End of added text)
Added text: (d) After the commissioners court provides notice of a hearing to establish or amend a county large computational load zoning district, a person may not begin construction or development of, or materially expand, redevelop, or materially change the use of, a county large computational load facility within the area described in the notice until the commissioners court: (End of added text)
Added text: (1) adopts or rejects the proposed district or amendment; or (End of added text)
Added text: (2) fails to take action on the proposed district or amendment before the 91st day after the date notice is provided. (End of added text)
Added text: Sec. 231.304. ZONING REGULATIONS. (a) The commissioners court may adopt reasonable zoning regulations within a county large computational load zoning district governing county large computational load facilities and large computational load, including regulations addressing: (End of added text)
Added text: (1) the location of a county large computational load facility; (End of added text)
Added text: (2) minimum lot size and tract dimensions; (End of added text)
Added text: (3) setbacks, buffers, landscaping, screening, and open-space requirements; (End of added text)
Added text: (4) measures reasonably necessary to protect nearby residential, educational, medical, agricultural, or environmentally sensitive uses from incompatible development; (End of added text)
Added text: (5) access roads, traffic mitigation, emergency access, and transportation impacts; (End of added text)
Added text: (6) noise, vibration, exterior lighting, and other off-site impacts; (End of added text)
Added text: (7) water supply, water conservation, cooling technology, wastewater service, stormwater management, drainage, floodplain management, and land subsidence risks, as applicable; (End of added text)
Added text: (8) fire protection, emergency response, law enforcement, and other public safety considerations; (End of added text)
Added text: (9) improvements, mitigation measures, capacity requirements, and service arrangements necessary to address project-related demands on county roads, bridges, drainage and flood-mitigation infrastructure, facilities, services, and county infrastructure capacity; (End of added text)
Added text: (10) disclosure of information necessary for the county to evaluate impacts on public infrastructure, water resources, emergency services, public safety, and county finances, subject to Chapter 552, Government Code; (End of added text)
Added text: (11) reasonable mitigation measures, road-use agreements, infrastructure agreements, and cost-sharing agreements reasonably related to project impacts and necessary to ensure that project-related county infrastructure, mitigation, remediation, and service costs are borne by the project rather than county taxpayers; (End of added text)
Added text: (12) performance bonds, closure bonds, site- restoration commitments, and other financial assurances necessary to ensure compliance and address abandonment, prolonged inactivity, decommissioning, demolition, remediation, removal of equipment or hazardous materials, and final site restoration; and (End of added text)
Added text: (13) any other reasonable land-use regulation directly related to the public health, safety, or welfare or the orderly development of the county. (End of added text)
Added text: (b) A zoning regulation adopted under this section must be reasonably related to a documented or reasonably foreseeable impact of a large computational load and may not be arbitrary or unrelated to a purpose authorized by this subchapter. (End of added text)
Added text: (c) The county may determine the amount, form, duration, issuer, renewal requirements, and conditions for release of a performance bond, closure bond, letter of credit, or other financial assurance. The amount must be reasonably related to the anticipated cost of compliance, mitigation, remediation, decommissioning, or site restoration. (End of added text)
Added text: (d) A county may not adopt regulations that directly conflict with a regulation adopted by a state agency. (End of added text)
Added text: Sec. 231.305. SPECIAL USE PERMIT. (a) The commissioners court may require a person to obtain a special use permit before developing, constructing, materially expanding, redeveloping, or materially changing a county large computational load facility within a county large computational load zoning district. (End of added text)
Added text: (b) An application for a special use permit may require: (End of added text)
Added text: (1) submission of site plans and engineering studies; (End of added text)
Added text: (2) information regarding traffic, water supply, wastewater, drainage, floodplain, emergency service, public safety, and county infrastructure impact analyses; (End of added text)
Added text: (3) information regarding anticipated electric demand, energization schedules, load growth, and electric infrastructure associated with the project; (End of added text)
Added text: (4) identification of any proposed water source and information regarding the availability of an adequate long-term water supply; (End of added text)
Added text: (5) supporting documentation prepared or certified by a professional engineer licensed in this state demonstrating that the proposed electric, water, wastewater, and other utility service and any required infrastructure improvements are reasonably capable of serving the projected demand of the project without impairing existing service; (End of added text)
Added text: (6) documentation that the project has been submitted to any applicable review or interconnection process required by the Public Utility Commission of Texas or administered by the Electric Reliability Council of Texas or another entity with jurisdiction; (End of added text)
Added text: (7) information reasonably necessary to identify and evaluate measures to mitigate documented adverse impacts within the county's authority under this subchapter. (End of added text)
Added text: (c) Before acting on a special use permit, the commissioners court may provide public notice and may hold a public hearing in accordance with procedures adopted by the court. (End of added text)
Added text: (d) The county may determine whether an application is complete and may require the applicant to submit additional information reasonably necessary to evaluate the application. A permit application is not considered filed until the county determines that the application is complete. (End of added text)
Added text: (e) The commissioners court may approve, conditionally approve, or deny a special use permit based on compliance with this subchapter and zoning regulations adopted under this subchapter. The county may make the final decision and any conditions imposed on the permit available to the public in a manner prescribed by the commissioners court. (End of added text)
Added text: (f) A permit may be denied if the applicant fails to demonstrate compliance with applicable zoning regulations or fails to adequately address a documented or reasonably foreseeable impact within the county's authority under this subchapter. (End of added text)
Added text: (g) After notice and an opportunity to cure, the county may suspend or revoke a special use permit for a material violation of this subchapter, a zoning regulation, or a condition of the permit. (End of added text)
Added text: (h) The county may issue a stop-work order if construction or development is occurring without a required permit or in material violation of a zoning regulation or permit condition. The order remains effective until the violation is corrected or the order is modified or withdrawn by the county or a court. (End of added text)
Added text: (i) The commissioners court may impose reasonable application, inspection, administrative, and professional-review fees including the reasonable cost of qualified consultants retained by the county, in an amount not to exceed the county's actual costs of administering this subchapter and reviewing the application. (End of added text)
Added text: (j) Information submitted under this section is subject to Chapter 552, Government Code. A county may not enter into an agreement requiring the county to withhold information from public disclosure except to the extent withholding is authorized by that chapter or other law. (End of added text)
Added text: Sec. 231.306. ELECTRIC REGULATION; PROJECT INFORMATION. (a) This subchapter does not authorize a county to regulate: (End of added text)
Added text: (l) electric rates or electric service; (End of added text)
Added text: (1-a) water rates or water service; (End of added text)
Added text: (2) generation permitting; (End of added text)
Added text: (3) transmission or distribution facility siting or interconnection standards; and (End of added text)
Added text: (4) the operations of the Public Utility Commission of Texas or the Electric Reliability Council of Texas; (End of added text)
Added text: (b) In evaluating a project under this subchapter, a county may request and consider information regarding: (End of added text)
Added text: (1) anticipated electric demand; (End of added text)
Added text: (2) the timing and scale of load growth; (End of added text)
Added text: (3) planned substations, transmission or distribution facilities, or other electric infrastructure associated with the project; (End of added text)
Added text: (4) the status of the project in any applicable review or interconnection process required or administered by the Public Utility Commission of Texas or the Electric Reliability Council of Texas; and (End of added text)
Added text: (5) measures proposed to reduce impacts on county infrastructure, emergency services, public safety, water supplies, and neighboring property. (End of added text)
Added text: (c) Nothing in this section prohibits a county from requesting or considering information concerning electric demand, energization schedules, substations, transmission or distribution infrastructure, interconnection status, reliability impacts, or curtailment capability for the purpose of evaluating land use, roads, drainage, water, emergency services, public safety, neighboring property, or county financial impacts. (End of added text)
Added text: Sec. 231.307. NONCONFORMING USES. (a) A county large computational load facility lawfully developed, or a large computational load lawfully operating before the effective date of a zoning regulation adopted under this subchapter may continue as a lawful nonconforming use. (End of added text)
Added text: (b) Zoning regulations adopted under this subchapter apply to a material expansion, redevelopment, or change in use of a nonconforming county large computational load facility or large computational load. In evaluating an expansion, redevelopment, or change in use, the county may consider the cumulative impacts of the existing county large computational load facility or large computational load and the proposed activity. (End of added text)
Added text: (c) A county large computational load facility or large computational load is not entitled to nonconforming-use status solely because land has been purchased, a project has been announced, utility service has been requested, or a preliminary application has been submitted. (End of added text)
Added text: Sec. 231.308. ENFORCEMENT. (a) A county may bring an action for injunctive relief to prevent or restrain a violation of this subchapter, a zoning regulation adopted under this subchapter, or a special use permit issued under this subchapter. (End of added text)
Added text: (b) A person who violates this subchapter, a zoning regulation adopted under this subchapter, or a special use permit issued under this subchapter is liable to the county for a civil penalty of not less than $500 or more than $10,000 for each violation for each day the violation continues. (End of added text)
Added text: (c) The county attorney or district attorney may bring an action under this section in a district court in the county. (End of added text)
Added text: (d) A county that prevails in an enforcement action under this section may recover reasonable attorney's fees, court costs, investigative costs, and expert-witness fees. (End of added text)
Added text: Sec. 231.309. CONSTRUCTION OF SUBCHAPTER. (a) This subchapter shall be liberally construed to accomplish its purposes of protecting the public health, safety, and welfare; promoting the orderly development of each county; and protecting neighboring property and public infrastructure; (End of added text)
Added text: (b) This subchapter may not be construed to authorize a county to regulate electric rates, electric service, wholesale electric markets, electric reliability standards, or a matter assigned by state or federal law to the Public Utility Commission of Texas, the Electric Reliability Council of Texas, or a federal agency. (End of added text)
Added text: Sec. 231.310. COORDINATION WITH COUNTY SUBDIVISION REGULATION. (a) Notwithstanding Section 232.001(h), a county may require an applicant for a plat or replat of property located within a large computational load zoning district to submit information, analyses, studies, plans, agreements, and financial assurances authorized by this subchapter or regulations adopted under this subchapter. (End of added text)
Added text: (b) Notwithstanding Section 232.0025, an application for a plat or replat of property located within a county large computational load zoning district is not considered complete, and the period within which the commissioners court or county authority must approve, conditionally approve, or disapprove the application does not begin, until: (End of added text)
Added text: (1) the county determines that the application includes the information required under this subchapter, regulations adopted under this subchapter, and Chapter 232; and (End of added text)
Added text: (2) any special use permit required for the development proposed in the application has been finally approved; (End of added text)
Added text: (c) The denial of a special use permit required for development proposed in a plat or replat application constitutes grounds for disapproval of the plat or replat application. (End of added text)
SECTION 2. This Act takes effect September 1, 2027.