SB 34Just filedHousing, property & local government

Lets counties zone and permit large data centers in unincorporated areas

The short version · AI summary

Counties could create zoning districts in unincorporated areas for large electricity users such as data centers, AI and crypto-mining operations. Commissioners courts could set rules on location, noise, water, roads and bonds, and require special use permits. Counties could charge fees and seek civil penalties of $500 to $10,000 per day for violations. Existing facilities could continue as nonconforming uses, but expansions would be covered. Counties could not regulate electric rates, generation permitting or grid interconnection. Takes effect September 1, 2027.

What it means for you

Most people would notice nothing directly. If you live near a proposed data center outside a city, your county could set rules on noise, water and roads and hold hearings.

One email when it moves, at most one a day. Unsubscribe in one click from any email.

Bill Facts

SB 34 · Filed Nov 9, 2026
Who it affects
  • Data center, AI and crypto-mining businesses in unincorporated areas
  • County commissioners courts
  • Landowners and neighbors near large electricity users
What changes
  • Counties could create zoning districts for large data-center-type electricity users in areas outside cities.
  • Counties could require special use permits, bonds and information on water, roads and power needs.
  • Counties could charge permit fees and seek fines of $500 to $10,000 per day for violations.
  • Plat approvals in these districts would wait for any required special use permit.
When it starts
September 1, 2027, if it becomes law
What it costs you
Developers could pay county permit and review fees up to the county's actual costs, and civil penalties of $500 to $10,000 per day per violation.
What it changes
6 tags, with the bill’s own words

What it changes

Each tag says one thing the bill changes, with the bill’s own words. A major tag reaches many people, a lot of money or a core right.

Gives communities more say

Major

Gives counties new zoning authority over large data-center-type developments in unincorporated areas.

Quoted from the bill text
the commissioners court may establish one or more county large computational load zoning districts and regulate the location and development of large computational load

Limits property owners

Major

Pauses development on affected land after hearing notice, up to 91 days, and zoning later restricts land use.

Quoted from the bill text
a person may not begin construction or development of, or materially expand, redevelop, or materially change the use of, a county large computational load facility within the area described in the notice until

Adds rules for business

Major

Counties may impose permit requirements and application information duties on large computational load businesses.

Quoted from the bill text
The commissioners court may require a person to obtain a special use permit before developing, constructing, materially expanding, redeveloping, or materially changing a county large computational load facility

Raises taxes or fees

Minor

Authorizes counties to charge applicants fees up to the county's actual costs.

Quoted from the bill text
The commissioners court may impose reasonable application, inspection, administrative, and professional-review fees including the reasonable cost of qualified consultants retained by the county

Gives a group a special break

Minor

Existing lawfully developed or operating facilities may continue despite later zoning regulations.

Quoted from the bill text
may continue as a lawful nonconforming use.

Raises taxes or fees

Minor

Creates a daily civil penalty for violating the subchapter, zoning rules or permits.

Quoted from the bill text
is liable to the county for a civil penalty of not less than $500 or more than $10,000 for each violation for each day the violation continues.

Reviewed by AI on Nov 12, 2026 · Reviewed text version I

How reviews work
  • The plain-words summaries and notes are written by AI, not by a person.
  • Every quote is checked against the bill, letter for letter, before it is shown. A note whose words cannot be found in the bill is dropped.
  • Editors may correct a summary, an area of life or a note.

Where it is now

A bill is filed first. Then it goes to a committee, a small group of lawmakers who study it. After that, the House and the Senate each vote.

  1. Step 1
    Filed
    A lawmaker turned the bill in.
    You are here.
  2. Step 2
    A committee studies it
    A small group of lawmakers studies the bill, holds a hearing and votes.
  3. Step 3
    One side votes
    The House or the Senate votes on the bill.
  4. Step 4
    The other side votes
    The other part votes too.
  5. Step 5
    The governor decides
    The governor signs the bill into law or vetoes it, which means says no.

The bill, word for word

This is the bill as filed. A bill that changes a law shows what it adds and what it removes.

The record

Bill text
Session
90th Legislature, regular session
Author
Judith Zaffirini
Subjects
County Government--Land Use & Zoning, PERMITS, PLATTING, Utilities--Electric
Documents
None yet
Witnesses
None yet

What happened so far

Every official action on this bill, newest first.

  1. Nov 9, 2026
    Filed
  2. Nov 9, 2026
    Received by the Secretary of the Senate
SB 34: Lets counties zone and permit large data centers in unincorporated areas | 51capitol