90R4296 CXP-D

By: Zaffirini S.B. No. 33

A BILL TO BE ENTITLED

AN ACT

relating to the recovery of costs related to providing electricity service to customers at a computational load site.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1. Sections 35.004(c-1) and (c-2), Utilities Code, are redesignated as Section 35.0041, Utilities Code, and amended to read as follows:
Added text: Sec. 35.0041. INTERCONNECTION OF AND COST RECOVERY FROM LARGE LOAD CUSTOMERS. (a) (End of added text) Deleted text: (c-1) (End of deleted text) The commission by rule shall ensure that a large load customer who is subject to the standards adopted under Section 37.0561 contributes to the recovery of the interconnecting electric utility's costs to interconnect the large load to the utility's system.
Added text: (b) (End of added text) Deleted text: (c-2) (End of deleted text) An electric cooperative or municipally owned utility that has not adopted customer choice shall pass through to a large load customer who is subject to the standards adopted under Section 37.0561 the reasonable costs to interconnect the large load in a manner determined by the electric cooperative or municipally owned utility.
Added text: (c) This subsection applies only to costs not recovered under Subsection (a) or (b). Notwithstanding Section 35.004, the commission by rule shall establish a system to: (End of added text)
Added text: (1) ensure that transmission costs of service attributable to a customer receiving electricity service at a computational load site are allocated to a separate transmission cost of service rate class composed only of that type of customer; and (End of added text)
Added text: (2) require each electric utility that provides distribution service to a customer described by this subsection to use a rate mechanism established by the commission for the purposes of Subdivision (1). (End of added text)
Added text: (d) For purposes of Subsection (c), "computational load site" means one or more buildings, structures, or installations at a single location that: (End of added text)
Added text: (1) primarily contains information technology infrastructure used for: (End of added text)
Added text: (A) creating, executing, and delivering software applications and services; (End of added text)
Added text: (B) artificial intelligence training, deployment, and delivery; (End of added text)
Added text: (C) adding virtual currency transactions to a distributed ledger; or (End of added text)
Added text: (D) other computational activities at a data center; and (End of added text)
Added text: (2) is supplied through electrical equipment that is connected to the bulk power system. (End of added text)
Added text: (e) In this section, "virtual currency" has the meaning assigned by Section 12.001, Business & Commerce Code. (End of added text)
Added text: (f) The system established under Subsection (c) may include requirements that customers subject to that subsection pay minimum demand charges, operate under contract terms specified by the commission, or meet any other requirements the commission determines necessary to ensure that transmission costs of service attributable to those customers are not paid by other customers. (End of added text)
SECTION 2. The Public Utility Commission of Texas shall adopt or revise rules as necessary to implement the changes in law made by this Act not later than September 1, 2028.
SECTION 3. This Act takes effect immediately if it receives a vote of two-thirds of all the members elected to each house, as provided by Section 39, Article III, Texas Constitution. If this Act does not receive the vote necessary for immediate effect, this Act takes effect September 1, 2027.