Sign in
← Back to SB 191
SB 191 · Version I

Introduced

Dated Nov 9, 2026

Underlined: added by this bill. Struck through: removed by this bill. Plain words stay as they are.

90R1342 CS-F

By: Hall S.B. No. 191

A BILL TO BE ENTITLED

AN ACT

relating to the interconnection of a facility in the ERCOT power region to certain other facilities.
BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF TEXAS:
SECTION 1. Section 37.051, Utilities Code, is amended by amending Subsections (c), (c-1), (c-2), and (c-3) and adding Subsection (c-4) to read as follows:
(c) Notwithstanding any other provision of this chapter Added text: except Subsection (c-1) (End of added text)Deleted text: , including Subsection (a) (End of deleted text), an electric cooperative is not required to obtain a certificate of public convenience and necessity for the construction, installation, operation, or extension of any generating facilities or necessary interconnection facilities.
(c-1) Added text: In this subsection, "facility" means a facility that consumes, generates, transmits, or distributes electricity. (End of added text) Notwithstanding any other provision of this title except Section 11.009, and except as provided by Subsection Added text: (c-3) (End of added text) Deleted text: (c-2) (End of deleted text), Added text: an electric cooperative, (End of added text) Deleted text: a person, including (End of deleted text) an electric utilityAdded text: , a (End of added text) Deleted text: or (End of deleted text) municipally owned utilityAdded text: , or another person (End of added text)Deleted text: , (End of deleted text) may not interconnect a facility Added text: in (End of added text) Deleted text: to (End of deleted text) the ERCOT Added text: power region to a facility located wholly or partly outside of this state or to a facility that is connected directly or indirectly with a facility located wholly or partly outside of this state, (End of added text) Deleted text: transmission grid that enables additional power to be imported into or exported out of the ERCOT power grid (End of deleted text) unlessAdded text: : (End of added text)
Added text: (1) the proposed interconnection will not subject the ERCOT power region to additional federal control or jurisdiction; (End of added text)
Added text: (2) the commission first determines that the proposed interconnection is in the public interest after considering: (End of added text)
Added text: (A) the technical attributes of the proposed interconnection; (End of added text)
Added text: (B) the expected costs to the public to install, operate, and maintain the interconnection; (End of added text)
Added text: (C) the results of relevant criteria adopted by the commission under Section 37.056(d); (End of added text)
Added text: (D) the results of a reliability assessment conducted by the independent organization certified under Section 39.151 for the ERCOT power region; and (End of added text)
Added text: (E) any other information the commission considers appropriate; (End of added text)
Added text: (3) the cooperative, utility, or person applies for a public interest determination from the commission under Subdivision (2) (End of added text) Deleted text: the person obtains a certificate from the commission stating that public convenience and necessity requires or will require the interconnection. The person must apply for the certificate (End of deleted text) not later than the 180th day before the date the Added text: cooperative, utility, or (End of added text) person seeks any order from the Federal Energy Regulatory Commission related to the Added text: proposed (End of added text) interconnectionAdded text: ; and (End of added text)
Added text: (4) after the cooperative, utility, or person obtains any order from the Federal Energy Regulatory Commission related to the proposed interconnection, the commission grants a certificate stating that public convenience or necessity requires or will require the interconnection (End of added text).
Added text: (c-2) (End of added text) The commission shall apply Section 37.056 in considering an application under Added text: Subsection (c-1) (End of added text) Deleted text: this subsection (End of deleted text). Deleted text: In addition, the commission must determine that the application is consistent with the public interest before granting the certificate. (End of deleted text) The commission may adopt rules necessary to implement Added text: Subsection (c-1) (End of added text) Deleted text: this subsection (End of deleted text). Added text: Subsection (c-1) (End of added text) Deleted text: This subsection (End of deleted text) does not apply to a facility that is in service on December 31, 2014.
Added text: (c-3) (End of added text) Deleted text: (c-2) (End of deleted text) The commission, not later than the 185th day after the date the application is filed, shall approve an application filed under Subsection (c-1) for a facility that is to be constructed under an interconnection agreement appended to an offer of settlement approved in a final order of the Federal Energy Regulatory Commission that was issued in Docket No. TX11-01-001 on or before December 31, 2014, directing physical connection between the ERCOT and SERC regions under Sections 210, 211, and 212 of the Federal Power Act (16 U.S.C. Sections 824i, 824j, and 824k). In approving the application, the commission may prescribe reasonable conditions to protect the public interest that are consistent with the final order of the Federal Energy Regulatory Commission.
Added text: (c-4) (End of added text) Deleted text: (c-3) (End of deleted text) Nothing in Subsection (c-1)Added text: , (End of added text) Deleted text: or (End of deleted text) (c-2)Added text: , or (c-3) (End of added text) is intended to restrict the authority of the commission or the independent organization certified under Section 39.151 for the ERCOT power region to adopt rules or protocols of general applicability.
SECTION 2. The changes in law made by this Act in Section 37.051, Utilities Code, apply only to an interconnection made on or after the effective date of this Act. An interconnection made before the effective date of this Act is governed by the law in effect when the interconnection was made, and the former law is continued in effect for that purpose.
SECTION 3. This Act takes effect immediately if it receives a vote of two-thirds of all the members elected to each house, as provided by Section 39, Article III, Texas Constitution. If this Act does not receive the vote necessary for immediate effect, this Act takes effect September 1, 2027.